Short deadlines leave little room for error. When the
government gives a contractor a short document approval deadline, the
contractor’s initial submission should strictly follow regulations because
there may not be time for required revisions, as an 8(a) joint venture found
out recently.
In that case, the only remaining approval the JV needed to
be awarded an 8(a) Army contract was the Small Business Administration (SBA)’s
approval of the 8(a) JV Agreement. Unfortunately for the JV, the SBA by law had
only five business days to approve the agreement. Because the JV had not
properly drafted the agreement it originally submitted to the SBA, five
business days was not enough time for the SBA to review and approve a revised
agreement. After time ran out on both the SBA and the JV, the Army awarded the
work to another 8(a).
The JV’s loss of the Army contract was unfortunate and probably
preventable. The agreement initially drafted by the JV and sent to the SBA for
approval omitted several provisions specifically required by SBA regulations. If
experienced legal counsel had been involved in the drafting of the JV agreement
from the start, these required clauses would have been included in the initial
JV agreement, and the short SBA deadline would most likely not have prevented the
JV from getting the work.
The decision shows that getting experienced legal counsel to
carefully draft foundation documents is essential to winning government contracts, especially when approval deadlines are short and leave little time
for error.
Terrence O'Connor is the Director of Government Contracts for Berenzweig Leonard, LLP, a business law firm in the D.C. region. Terry can be reached at toconnor@berenzweiglaw.com.